The Largest U.S. Grid Operator Puts 1,200 Mostly Solar Projects on Hold for Two Years
View
Date:2025-04-17 12:18:29
The nation’s largest electrical grid operator has approved a new process for adding power plants to the sprawling transmission system it manages, including a two-year pause on reviewing and potentially approving some 1,200 projects, mostly solar power, that are part of a controversial backlog.
PJM Interconnection operates a competitive market for wholesale electricity in all or part of 13 states and the District of Columbia, from Virginia to northern Illinois. Its plan is the result of work over the past year by PJM and what it calls its stakeholders, according to a press release from PJM. They include electric utilities, electric transmission owners, state and consumer interests, and solar and wind developers.
“These changes represent a landmark accomplishment for PJM stakeholders and staff that establishes a better process to handle the unprecedented influx of generation interconnection requests and is critical to clearing the backlog of projects,” said PJM President and CEO Manu Asthana.
PJM remains committed to a strategy of “decarbonization policies while preserving reliability and cost-effectiveness,” Asthana said.
But the backlog, and a two-year pause on so many projects with the potential for even longer delays on new proposals, has frustrated a number of renewable energy developers.
In January, an outspoken Adam Edelen, a former Kentucky state auditor who runs a company working to bring solar projects and jobs to ailing coal communities in Appalachia, said he was concerned that “the kink in the system” was helping to delay effective climate policy in the United States. “The planet does not have time for a delay,” he said at the time.
Approval delays were putting solar developers in a financial bind and calling into question the Biden administration’s goal of having a carbon-free electricity grid in just 13 years, he cautioned.
Edelen late Thursday afternoon said he was still reviewing PJM’s announcement, which went out on Thursday.
“The current situation is preventing clean energy projects from coming online and is unsustainable,” said Kat Burnham, a principal of Advanced Energy Economy, a trade group for clean energy businesses that has expressed frustration with the situation. “While the reforms aren’t perfect, the updated process will help mitigate the project backlog. Any further delays would be worse for advanced energy projects and America’s clean energy transition.”
A PJM spokesman, Jeffrey Shields, said PJM would send its plan to the Federal Energy Regulatory Commission in May. FERC has 60 days to act on the plan, or it could not act and the plan would go into effect, Shields said.
Over the last four years, PJM officials have said they have experienced a fundamental shift in the number and type of energy projects seeking to be added to a grid, each needing careful study to ensure reliability. It used to be that PJM would see fewer, but larger, fossil fuel proposals. Now, they are seeing a larger number of smaller, largely renewable energy projects.
In all, there are about 2,500 projects awaiting action by the grid operator, which is based in Valley Forge, Pennsylvania, outside Philadelphia.
PJM has put forward a two-phased solution.
A new approval process will put projects that are the readiest for construction at the front of the line, and discourage those that might be more speculative or that have not secured all their financing.
Then, an interim period will put a two-year delay on about 1,250 projects in their queue—close to half of the total—and defer the review of new projects until the fourth quarter of 2025, with final decisions on those coming as late as the end of 2027.
Shields said that during the two-year transition, PJM will continue to work on more than 1,200 projects, which include more than 100,000 megawatts of renewable energy. “There is no shortage of renewables poised to come online,” he said.
The backlog, caused in part by the explosion of interest in solar energy, varies by state. Earlier this year, there were hundreds of projects waiting for review in states like Pennsylvania and Virginia, and dozens in states like Kentucky and West Virginia.
The Pennsylvania Energy Office was still reviewing the plan, said its spokesman, Jamar Thrasher, on Thursday.
“We support the changes PJM is implementing to create a more efficient and effective process, which will allow for the timely interconnection of generation to the PJM grid while ensuring reliability,” said Tammy Ridout, spokeswoman for the Ohio-based utility AEP.
“These improvements are critical to handle the influx of interconnection requests we have seen in recent years and will see for the foreseeable future,” said Ken Seiler, PJM vice president of planning, in a written statement. “This plan represents a real compromise among many different interests to get renewable and other projects through the queue as fast as possible and give developers a clearer picture of their costs and timelines.”
veryGood! (96457)
Related
- 'Survivor' 47 finale, part one recap: 2 players were sent home. Who's left in the game?
- Golden retriever puppy born with green fur is now in the viral limelight, named Shamrock
- Robert Irwin, son of 'Crocodile Hunter', reveals snail species in Australia named for him
- Fleeing suspect fatally shot during gunfire exchange with police in northwest Indiana
- Angelina Jolie nearly fainted making Maria Callas movie: 'My body wasn’t strong enough'
- Wild horses to remain in North Dakota’s Theodore Roosevelt National Park, lawmaker says
- The Best Waterproof Jewelry for Exercising, Showering, Swimming & More
- Net neutrality restored as FCC votes to regulate internet providers
- All That You Wanted to Know About She’s All That
- 5th person charged in killing of 2 Kansas moms, officials say
Ranking
- Biden administration makes final diplomatic push for stability across a turbulent Mideast
- Summer House's Carl Radke Reveals His Influencer Income—And Why Lindsay Hubbard Earns More
- Building at end of Southern California pier catches fire, sending smoke billowing onto beach
- Divided Supreme Court appears open to some immunity for president's official acts in Trump 2020 election dispute
- Romantasy reigns on spicy BookTok: Recommendations from the internet’s favorite genre
- Celebrate National Pretzel Day: Auntie Anne's, Wetzel's Pretzels among places to get deals
- Massive fire seen as Ukraine hits Russian oil depots with a drone strike
- Kentucky appeals court denies Bob Baffert-trained Arkansas Derby winner Muth to enter Kentucky Derby
Recommendation
New Mexico governor seeks funding to recycle fracking water, expand preschool, treat mental health
New York City to require warning labels for sugary foods and drinks in chain restaurants
Hamas releases video of injured Israeli-American hostage Hersh Goldberg-Polin
Bears have prime opportunity to pick a superstar receiver in draft for Caleb Williams
Paula Abdul settles lawsuit with former 'So You Think You Can Dance' co
Golden State Warriors star Steph Curry named 2023-24 NBA Clutch Player of the Year
As some universities negotiate with pro-Palestinian protestors, others quickly call the police
Luna County corporal is charged for his role in deadly 2023 crash while responding to a call